SRF FOR NEUTRINO FACTORIES

2001 
The Neutrino Factory calls for nearly 500 meters of 200 MHz SRF cavities to provide 7.5 GV. Such a facility is more demanding than the largest SRF installation to date, i.e., LEP-II, where 500 m of niobium-coated copper cavities provided more than 3 GV of acceleration. Based on the high real estate gradient desired to minimize muon loss, superconducting cavities are selected to provide active gradients of 15 – 17 MV/m, and a real estate gradient of 7.5 MV/m. At such high gradients, the peak RF power demand for copper cavities would become prohibitively expensive. By virtue of low losses, SC cavities can be filled slowly (rise time 3 ms) reducing the peak power demand to roughly half MW per cell.